Week 2 Update Neighbors House

After completing the bulk of the demo last week my main goal has been towards getting the new roof on. I always start with the new roof first (and foundation if needed) on any major remodel so if there were any leaks previously it wont trash any new stuff going in. Before I can get the roof on this house, I have to add the porch and room addition so it’s been my main focus to get these taken care of first. I had to move the gas meter back 40 feet from the house but luckily the power company showed up Monday and obliged so I got started with no delay. The porch came out really good as it completely changed the look of our house. In this historic neighborhood everyone loves the big front porches and they are an important feature in order to maximize retail sales price. I mimicked the original house design with the 30” eaves and open rafter tails. There are about 10 different Craftsman style home models in our neighborhood but unfortunately this one doesn’t come with the traditional porch so we knew we had to add it. The rear addition is the major change of this house, it will be approximately 620 square feet and contain a utility room, master bedroom, master bath, hallway and walk in closet. Once again to obtain maximum retail sales price these are things that today’s buyer will expect. We will also be giving them a walk-in food pantry and double vanities in the bath, all popular amenities to consider when given the opportunity to remodel. I was fortunately able to design around the big pecan tree so after we are done I plan to do a cool deck around the tree with a circular bench and French doors leading from the master suite. We’ve gone through 6 dumpsters so far, 3 being filled with dirt from the excavation I had to do with the Bobcat for the addition. Monday I have an engineer inspecting my foundation and issuing a certificate, which the City of San Antonio requires for our permit and then we’ll be free to start framing. Do you want to learn exactly how someone pulled down $155,510 his first year Flipping Houses in a recession? Visit our friend’s blog and see. Congratulations bro!

5 Yards of Concrete & 200 lbs of Rebar Later

5 Yards of Concrete & 200 lbs of Rebar Later

piers

I finished the 15 concrete piers today for the 435 s.f. master suite addition. There are 3 rows of 5 with 7 foot spacing. After the bobcat grading I dug 24” holes, 2 feet deep with an auger.

At the bottom of the holes I placed #4 rebar in a tic tac toe pattern, 3 pcs each way. Then I filled the holes up 18” with 4000 psi concrete to make the footing. For the pier I placed 2 more pieces of rebar sticking straight up through 10” sonitubes.

I left these 2 pieces of rebar a little high so the sill beams can lay inside them. Finally I filled the sonitubes with more concrete to complete the pier. I have to reflect for a minute on how easy this is in Texas vs. California which has all the earthquake codes and bureaucratic red tape.

The City of San Antonio only requires an Engineer’s approval letter for the foundation inspection of my building permit, (which I pulled over the counter). He comes out twice, once to inspect the hole depth then secondly after the beams are sitting on the piers.

Try pulling a permit in San Diego. Drop off your plans, wait for months and prepare to jump through some hoops! The framing will start on Monday. Stay tuned.

Arch Arch Baby

Arch Arch Baby

Open Floorplan Arches

Here’s how the new floorplan is playing out after our drastic changes. As you can see we’ve opened up 4 main walls with dramatic arches. It has really given the home a more functional layout and brings in a lot more light.

Under the House

We also got started on the foundation repair which is always 2nd on our list to do after demo. It was important on this project to get everything level before we even start the room addition and it needs to be lifted 3 inches in some areas. The house sits on 38 cedar posts, these posts are actually trunks of cedar trees which is common in this part of Texas.

Each post is 5 feet tall, 3 feet of which is buried in the ground sitting on a concrete pad. Cedar is naturally resistant to termites, however, after 85 years and possible drainage problems the cedar gets rotten as you can see in the above photo.

In order for us to level the house, we are replacing all 38 posts. We had 4 workers under the house digging the holes to pull out the rotten posts. How would you like to have to crawl under the house with only a damp dark 24 inches of clearance and dig 38 3-foot deep holes? These guys are rad.